a construction worker estimates that a kitchen remodel will take 1 person 108 hours. If 3 people work on the job for hours a day, how many days will it take for them to complete the job?

Respuesta :

Divide 108 by 3 find out how many hours then divide the hours by 24 so it will take them 1.5 days