You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure. The cycle time of the line is 10 minutes, and the sum of all that tasks required on the line is 60 minutes. Which of the following is the correct value for the resulting line's efficiency? A. 0.500B. 0.650C.0.750D. 0.850E. None of these

Respuesta :

Answer:

Efficiency will be 0.75 so option (c) will be correct option

Explanation:

We have given Total time for all task = 60 minutes

Actual Number of workstations = 8

Cycle time = 10 minutes

Efficiency is given by  

[tex]Efficiency(\eta ) =\frac{total\ time\ for\ all\ task}{number\ of\ work\ station\times cycles\ time}=\frac{60}{8\times 10}=0.75[/tex]

So option (c) will be the correct option